Fire permits in San Diego: how long they take and who pulls them

How long fire alarm, sprinkler and other fire permits take in the City of San Diego, how many are filed, and who pulls them, from 6,680 fire permits filed since January 1, 2024. Updated weekly from city permit records.

At a glance

Time to issue runs from the day the application is created to the day the permit is issued. It includes time spent waiting on the applicant to answer plan-check comments, so it's the whole calendar, not just the city's review.

How long each fire permit takes

PermitMedian time to issueMost permits (middle half)Permits measured
Fire alarm23 days12–55 days2,525
Fire sprinkler (suppression)30 days14–74 days2,245
Underground fire line110 days47–204 days192
Kitchen hood suppression22 days11–44 days216

Standalone permits versus permits filed with a building project

17% of San Diego's fire permits are standalone fire projects, such as a new alarm panel or a sprinkler retrofit. The rest are filed as part of a larger building permit, such as a remodel or new building, and move through review with it.

PermitStandaloneWith a building project
Fire alarm27 days22 days
Fire sprinkler (suppression)53 days29 days
Underground fire line65 days159 days
Kitchen hood suppression20 days24 days

Standalone sprinkler permits took a median of 53 days, against 29 days when filed with a building project. Underground fire lines run the other way: 159 days with a building project, 65 days on their own, probably because they're tied to site and utility work on larger projects.

Fire permits by year

Year filedAlarmSprinklerUndergroundKitchen hoodMedian time to issue
20241,0989288710626 days
20251,1251,1331089429 days
2026 (to date)9348921047126 days (filed by May 1, 2026)

170 alarm permits in this period were for switching a fire alarm's monitoring connection from a copper phone line to cellular, as carriers retire traditional landlines. If a building's alarm still reports over a phone line, expect to need one of these.

What kinds of buildings

Building or project typeFire permitsAlarmSprinkler
Tenant improvements (remodels)3,8141,6171,968
Apartment buildings (5+ units)486166214
Apartment alterations (3+ units)261128132
Accessory dwelling units1303888
Industrial buildings1024451
Other nonresidential alterations953851
Condo buildings (5+ units)805123
Nonresidential accessory structures702441

Remodels dominate: 57% of fire permits are tenant improvements, where alarm devices and sprinkler heads are moved and added as a space is rebuilt for a new tenant.

Planning a fire protection project in San Diego

  1. Budget a month for alarm and sprinkler permits, and up to three months or more for an underground fire line. Start the underground permit first if the project needs one.
  2. Answer plan-check comments quickly. The times above include the applicant's response time, so a slow resubmittal adds directly to the wait.
  3. Check whether your alarm still uses a phone line. Cellular conversions need a permit too.
  4. Hire a licensed contractor and confirm the license before you sign. 22 licensed fire protection companies are based in San Diego; check any contractor's license here.

Most active listed contractors

Ranked by fire permits filed in San Diego since January 1, 2024. San Diego publishes the permit holder's name but not a license number, so this counts only permits whose holder exactly matches the name of a C-16 contractor in our directory (36% of permits that name a holder). Alarm-only companies licensed as electrical (C-10) contractors aren't in the directory yet. Activity, not quality; no company pays to appear here.

How these numbers are calculated

Frequently asked questions

How long does a fire sprinkler permit take in San Diego?
A median of 30 days from application to issue, with most taking 14–74 days, based on 2,245 City of San Diego permits. Standalone sprinkler permits took 53 days.
How long does a fire alarm permit take in San Diego?
A median of 23 days from application to issue; most take 12–55 days.
How long does an underground fire line permit take in San Diego?
A median of 110 days, and a quarter take longer than 204 days. It's the slowest fire permit in the city, so start it first.
How many fire permits does San Diego issue each year?
2,219 fire permits were filed in 2024; 2,460 fire permits were filed in 2025, about half alarm and half sprinkler.
Where do these San Diego fire permit figures come from?
From City of San Diego Development Services permit records published as open data, refreshed weekly. San Diego doesn't publish costs for fire permits, so these figures cover timing and volume.